A - Simplified startup

The start up sequence of a CCGT Plant with SSS Clutch.
(back to top)
• Standard GT Start
The SSS Clutch allows the GT to be run up independent from the ST.
(back to top)
• Reduced time to generation
The time from start initiation to synchronising the generator to the grid
is reduced and can be accurately predicted as it is independent of steam
turbine temperature.
(back to top)
• No cooling steam required
During the GT startup sequence no steam is available from the HRSG and
so unless the steam turbine is uncoupled a steam supply is needed to cool
the steam turbine blades and provide sealing during the run up.
(back to top)
• Reduced starting power
The power required to start the machine is reduced as only the gas turbine
and generator are rotated by the gas turbine starting system.
(back to top)
• Reduced emissions
The reduced starting time of the gas turbine results in reduced emissions
during the start sequence when emissions may be higher than at efficient
high loads.
(back to top)
• Standardised design
As the steam turbine is mounted with its own axial bearing there are less
constraints on the turbine and a more standard design can be utilised.
Where differing steam cycles are offered various steam turbine designs
can be accommodated more readily.
(back to top)
• Simplified torsional analysis
The steam turbine is disconnected during gas turbine acceleration therefore
the condition when the gas turbine is driving the steam turbine does not
have to be considered.
(back to top)
B - Increased flexibility
(back to top)
• Simplified commissioning
Assuming that the plant has a 100% steam bypass facility the GT can be
commissioned as a simple cycle machine without rotating the steam turbine.
Gas turbine performance can be proven and quantified before commissioning
of the steam turbine is begun.
(back to top)
• Steam turbine trips do
not stop power generation
Because the steam turbine can be shutdown independently from the GT any
tripping of the steam turbine system does not necessarily entail a GT
trip. Clearly GT trips are a particular concern because of the total loss
of power generation capability and their effect on maintenance schedules.
(back to top)
• Maintenance of GT during
ST cooling
An important option that can be provided when using an SSS Clutch is to
allow the gas turbine to be stopped whilst the steam turbine continues
to be rotated by its own turning gear. This feature can be important as
generally the time that the steam turbine must remain on turning gear
after shutdown is significantly longer than the time required by the gas
turbine. Outage times could be reduced by starting gas turbine maintenance
whilst still turning the steam turbine.
(back to top)
C - Optimised shutdown

The shutdown sequence of a CCGT Plant with SSS Clutch.
(back to top)
• Shutdown ST at reduced
GT power
During a normal shutdown of the machine the steam turbine can be shutdown
before the gas turbine. This is generally arranged whilst there is some
load remaining on the gas turbine to prevent the reduced gas turbine exhaust
temperatures causing the steam turbine temperatures to drop and therefore
delaying any subsequent starts.